How To Solve the Problem of Stamping Damage of Can Making Machine?

The problem of stamping damage of canning machines will lead to product scrapping and remaking, which will increase the company's costs. To solve the problem of stamping damage, it is necessary to control the molds, operating techniques, etc.
Feb 13th,2025 435 Views

The problem of stamping damage of canning machines will lead to product scrapping and remaking, which will increase the company's costs. To solve the problem of stamping damage, it is necessary to control the molds, operating techniques, etc.
Canning & Stamping

1. Control the mold:

  1. When the mold is found to be abnormal during the pattern making, write an equipment/mold maintenance application form within 4 hours and submit it to the technical department manager, and the manager will convene relevant personnel to confirm the handling method;

  2. The warehouse prepares the mold two days in advance according to the stamping day plan;

  3. When the machine repair receives the mold, it must be registered on the mold collection and return registration form, and the mold warehouse manager will issue the mold according to the product name;

  4. The machine repair master returns the mold to the warehouse according to the number of molds received. If it cannot be returned to the warehouse, the return time must be indicated on the mold collection and return registration form;

2. Control the operator:

  1. When the machine repair master receives the mold abnormality, he must preliminarily determine the time when the mold can be repaired and inform the production team leader so that the team leader can make personnel arrangements. When the machine mold abnormality is not handled for more than two hours, the mechanic needs to report it to the mechanic supervisor for handling; when the mechanic supervisor handles the abnormality for more than 1.5 hours and fails to handle it, it needs to be reported to the technical manager for handling;

  2. When the mold of an order is produced, the mechanic must first reserve a product in the mold cavity, then apply anti-rust oil to clean it, remove the mold, and close the upper and lower molds;

  3. After the mold is debugged, the mechanic will hand over the first product to the quality department for confirmation, and the quality department will fill in the mold first inspection record form. After the quality control and production team leader confirm that the first product is OK, mass production can be carried out;

  4. When the mold abnormality is due to the need for outsourcing processing of accessories, if it is not normal for more than 8 hours, the mold needs to be treated with anti-rust oil, and a mold parts processing application form needs to be written;

  5. If the mold is abnormal before returning to the warehouse, it needs to be repaired before it can be returned to the warehouse.

I m Steve, a professional with 15 years of experience in the metal packaging industry. We focus on providing customized, high-quality metal packaging solutions to meet our customersneeds. If you have any questions, please contact us.
Steve Xu, a professional with 15 years of experience in the metal packaging industry

Steve Xu

Senior Sales Manager
Leave a message
FirstName*
LastName*
Email*
Message*
We use Cookie to improve your online experience. By continuing browsing this website, we assume you agree our use of Cookie.
Message Us